On most construction projects the programme is built around the building. Trades follow each other through the space in the most efficient order and the client moves in at the end.

On a live healthcare site the building is already full. Wards stay open, clinics keep their lists, theatres run their sessions, and patients and visitors keep arriving through the same doors the contractor needs to use. The programme has to be built around all of that, and the people who know what can and cannot stop are clinical, not construction.

This guide sets out how we approach construction in a live healthcare environment as client-side project managers: the decisions worth making before anyone is on site, how phasing and decant are planned, how the governance works, and what the estates team should expect from whoever is managing the project for them.

What makes construction on a live healthcare site different?

Three things, and they change the order in which the project has to be planned.

The service cannot stop. A ward or a clinic is not a tenant that can be asked to work from home for a fortnight. Every interruption has a clinical consequence, a cost and an owner who has to agree to it.

The site is shared. Corridors, lifts, loading bays and car parks serve patients, staff, deliveries and the contractor at the same time. Segregation, hoarding lines and access routes are design decisions, not site decisions.

The environment is controlled. Infection control, air quality, noise, vibration and dust all have clinical limits that sit above anything a normal construction site would work to. The relevant Health Technical Memoranda (HTM) and Health Building Notes (HBN) set the standards the design and the method have to meet, and the Trust's own infection prevention and control team will have a view on every phase. The current published versions should be checked with the Trust at project initiation and changes should be considered during the life of the project.

Put those three together and the conclusion is simple. The programme on a live healthcare site is a clinical plan with a construction plan inside it, rather than the other way round.

Hospital corridor with a temporary partition separating a refurbishment zone from the corridor still in use

Which decisions have to be made before anyone is on site?

The expensive mistakes on live healthcare schemes are nearly always decisions that were not made early enough. These are the ones we ask for during stages 0 / 1, before the design is developed.

DecisionWho holds itWhy it has to come first
Which services cannot be interrupted, even for an hourClinical leadsIt defines the phasing. Everything else works around these.
Which services can move, and where toClinical leads, estates and operationsDecant space is the single biggest constraint on sequence.
Who can authorise a shutdown, and with how much noticeNamed clinical and estates leadsThis decision most often decides the programme. If it takes three weeks to arrange a one-day shutdown, the programme has to be built from that.
What the infection control constraints are for each phaseInfection prevention and control teamThey determine hoarding, air handling, access routes and working hours.
What the out-of-hours and weekend working rules areEstates, clinical leads, the contractorNight and weekend working is often the only way to touch certain areas. It has a cost and a noise limit.
Who speaks for the clinical teams on the project boardTrust leadershipOne accountable voice, with authority, rather than a different consultee at every meeting.

Agree those and the design team has a set of real constraints to design to. Leave them until tender and the contractor prices the uncertainty, then finds out the answers on site.

How should the phasing and decant be planned?

Phasing on a live site is a sequence of moves, and each move has to be agreed with the people who use the space.

Start with the services that cannot move. They fix the areas of the building that are untouchable, or touchable only at night, at weekends or in a planned shutdown window. Then work out which services can be decanted, where to, and for how long. Decant space is nearly always the limiting factor: there is rarely a spare ward, and temporary accommodation has its own cost, programme and approvals.

From there the phasing builds itself. Each phase has an area, a decant plan, an access route, a hoarding line, an infection control method and a set of shutdowns with named approvers. The contractor's programme sits inside that, rather than driving it.

Three things we would expect any client-side project manager to insist on:

  1. A phasing plan that the clinical leads have signed, not just seen. If the ward manager has not agreed the move, it has not been agreed.
  2. A shutdown register. Every planned interruption to a service or a system, with the date, the duration, the approver and the notice period, maintained from the start and reviewed at every project meeting.
  3. A communications plan for staff and patients that is written by the Trust with the project team, so the message about noise, access and timing reaches the right people before each phase starts.
Ward floor plans with phasing zones and a programme laid out on a meeting table during planning

What does governance look like on a healthcare project?

Governance is the structure that decides who decides, and on a live clinical site it has to be tighter than most. A decision taken informally in a corridor about a shutdown or an access route can close a service.

We agree the decision rights as soon as possible on a project. With our support, the client decides the brief, the budget, the procurement route and contract form, the acceptance of major risk, and anything that changes the shape of the scheme. On a healthcare scheme that list extends to every service interruption and every decant move, because those are construction decisions with a clinical consequence.

We run the programme, the consultant team, the shutdown register and the reporting, and every decision that is the client's reaches them as a decision request: the options, the cost and programme effect of each, the cost of waiting and a recommendation. Our monthly report ends with Decisions Required, so the estates lead and the board can see in two minutes what is being asked of them and by when.

We manage it, you govern it. On a live site that line describes how the clinical service stays in control of its own building.

What should the estates team expect from the project manager?

A client-side project manager on a healthcare scheme should be doing four things visibly from the first month.

Asking the clinical questions early. Which services cannot stop, who signs off a shutdown, where the decant goes. If those questions have not been asked before the design is fixed, the project is being planned as a normal building job.

Owning the shutdown register and the phasing plan, and bringing changes to the people who have to approve them with enough notice to be a decision rather than a fait accompli.

Keeping the infection control team inside the project, not consulted at the end. Their constraints are design inputs.

Saying early when a date will not hold. On a live site a missed date can mean a service stays decanted for another month. The most useful thing a project manager can do is shorten the gap between a problem becoming visible and it reaching the person who can decide what to do about it.

When should a project manager be appointed on a healthcare scheme?

Earlier than most estates teams think. By tender, most of what decides the cost and the programme on a live site has already been fixed: the phasing logic, the decant plan, the survey information and how complete the design is. A project manager appointed at brief and feasibility can help shape those while every option is still open. One appointed later starts by managing decisions they had no part in. We have written separately about when to appoint a project manager, and the logic is sharper still on a live site.